Floor coating common sense of how to choose the appropriate type of floor

1. floor coating common sense of epoxy floor surface treatment 1, the newly completed ground must go through certain maintenance before construction, about 28 days. 2, remove the surface of the laitance, old paint and adhesion of garbage debris. 3, thoroughly remove the surface of the oil, with grams of oil king cleaning agent treatment. 4. Clear the accumulated water and dry the tide thoroughly. 5. The cleaning of the surface needs to be done with a dust-free sweeper and a large vacuum cleaner. 6. The allowable gap on the flat surface is 2~2.5mm, the water content is below 6%, and the PH value is 6~8. 7, epoxy floor surface of the hair, need to use a dust-free grinder to complete, and thoroughly clean with a vacuum cleaner. 8. Apply putty to fill the batch of scraping on the holes and obvious depressions on the surface of the epoxy floor. After solid work, polish and vacuum. 2. Floor Coating Common Sense Finishing Strong Sealing Coatings 1, in the treatment of clean, smooth concrete surface, the use of high-pressure airless spraying or roller coating, epoxy closed primer 1. 2, the floor sealer has a strong permeability, when the primer should be added a certain amount of diluent, so that the diluted primer can penetrate into the base, enhance the adhesion of the coating and the base, the coating must be continuous, not interrupted, the coating amount to the surface just saturated. 3. Local leakage coating can be applied with a brush. The excess primer on the surface must be polished before the construction of the next process. 3. floor coating common sense of batch scraping, batch scraping material In the dry (25 ℃, about 4 hours) after the primer surface using two batches of putty method, to ensure that the epoxy floor wear resistance, pressure resistance, collision, water, mineral oil, acid and alkali solution and other properties, and adjust the ground flatness. 1, with 70~140 purpose quartz sand and solvent-free epoxy batch scraping material, as the first putty, to fully stir evenly, scraping level. This road is mainly used to enhance the wear resistance and compressive properties of the ground. 2. Grind the first putty with a sand bag type dust-free rolling sander and vacuum it for cleaning. 3, with 200~700 purpose quartz sand and solvent-free epoxy batch scraping material, as the second putty, to be fully stirred evenly to enhance the wear resistance and flatness of the ground. 4. Grind the third putty with sand bag type dust-free rolling mill, and vacuum and clean it. 5. After the two putty are dry, if there are pitted surfaces and cracks, they should be repaired first, and then polished with a flat sander to smooth them and vacuum them for cleaning. 6. The number of quartz sand used shall be determined by the field engineer according to the specific conditions of the ground. 4. floor coating common sense of finishing epoxy floor middle layer Finish the intermediate layer on the polished and cleaned putty surface (20 ℃,24 hours). 1, the finishing method can be used brush, batch scraping, high pressure airless spraying, large area construction to high pressure airless spraying is the best. (Spraying pressure is 20 ~ 25Mpa). 2, this time can make the ground more flat, more convenient to find the ground still exist defects, so that the surface layer construction leveling. 3. This time is also convenient for Party A to arrange equipment installation, etc. 5. floor coating common sense of finishing epoxy floor surface layer 1, in the middle layer of hard work (20 ℃,7 days), the epoxy solvent-free epoxy floor surface coating, coating method with batch scraping and high pressure airless spraying, but with high pressure airless spraying is appropriate. 2. Before coating, the middle layer should be polished and vacuumed with a sand bag type dust-free rolling sander. 3. If Party A has installed and debugged the equipment after the middle layer has been worked hard, resulting in new defects on the ground, it shall use batch scraping materials for leveling, polishing, vacuuming and cleaning. 4, the surface layer after spraying, such as the existence of bubbles in the application of defoaming roller, rolling back and forth on the epoxy floor, and finally let its own leveling can be. 6. floor coating common sense of construction matters needing attention 1, the construction site of the ambient temperature should be higher than 5 ℃, the relative humidity is less than 85% before construction. 2, the construction of the construction site, time, temperature, relative humidity, epoxy floor surface treatment, materials, such as the actual record, for inspection. After the coating construction, the relevant equipment and tools should be cleaned immediately. Safety technical requirements for common sense of 7. floor coating 1. The warning tape and warning signs shall be hung around the construction site. 2. No open fire operation and smoking are allowed within 10 meters around the construction site. 3, the use of high-pressure airless spray pump should be properly grounded. 4. Paint and thinner should be placed in a well-ventilated warehouse. 5, pay attention to personal protection when working. 6. Special personnel shall be responsible for the use of electric tools, and the power supply shall be cut off before leaving the field. The use and maintenance of 8. floor coating common sense 1, when the paint construction is completed, do not use in the maintenance period, and must strengthen the ventilation equipment and fire prevention measures. 2, epoxy floor use, production personnel are not allowed to wear leather shoes with nails to walk on it. 3. All working instruments must be placed in a fixed special frame. It is strictly prohibited for metal parts with acute angles to collide with the ground, causing damage to the ground paint. 4, workshop installation equipment and other major objects must use lifting machinery, in contact with the ground support point should have thick rubber and other software materials pad properly, it is strictly prohibited to use iron pipes and other metals to drag equipment on the ground. 5. When high-temperature operations such as electric welding are carried out in the workshop, asbestos cloth and other refractory materials shall be applied to pave the place where electric welding sparks splash to prevent the paint from burning out. 6, once the epoxy floor is damaged, the timely use of paint repair, so as to avoid oil through the damage to penetrate into the cement, causing a large area of paint off. 7. When cleaning the ground in a large area in the workshop, do not use strong chemical solvents (toluene, banana water, etc.) to generally use detergents, soap, water, etc., and use a cleaning machine. In the absence of a cleaning machine, sawdust can be used and then cleaned. 8, winter construction, the ambient temperature is lower than 5 degrees Celsius, can be used in winter solvent-free epoxy industrial epoxy floor coatings. 9, epoxy floor surface coating formula must be strictly in accordance with the standard, the use of electronic scales according to the weight ratio, so as to ensure the quality of the floor! Guangzhou Zhiye Chemical Co., Ltd. has been focusing on floor paint for 23 years. As a professional floor paint manufacturer established in the early stage of China, Zhiye has taken the lead in passing ISO management in the industry. It has always insisted on creating the greatest value for customers with continuous innovation, specializing in R & D, production, sales and application services of high-quality epoxy resin floor. Address (Address): 4/F, Deputy Building, Kerui Building, 336 Qingnian Road, Huangpu District Development Zone, Guangzhou Tel: 020-82057070 Web: www.gzzeal.com www.gzzeal.com 020-82057070 Long press scan code can be concerned


1. floor coating common sense of epoxy floor surface treatment

1, the newly completed ground must go through certain maintenance before construction, about 28 days.

2, remove the surface of the laitance, old paint and adhesion of garbage debris.

3, thoroughly remove the surface of the oil, with grams of oil king cleaning agent treatment.

4. Clear the accumulated water and dry the tide thoroughly.

5. The cleaning of the surface needs to be done with a dust-free sweeper and a large vacuum cleaner.

6. The allowable gap on the flat surface is 2~2.5mm, the water content is below 6%, and the PH value is 6~8.

7, epoxy floor surface of the hair, need to use a dust-free grinder to complete, and thoroughly clean with a vacuum cleaner.

8. Apply putty to fill the batch of scraping on the holes and obvious depressions on the surface of the epoxy floor. After solid work, polish and vacuum.

2. Floor Coating Common Sense Finishing Strong Sealing Coatings

 

1, in the treatment of clean, smooth concrete surface, the use of high-pressure airless spraying or roller coating, epoxy closed primer 1.

2, the floor sealer has a strong permeability, when the primer should be added a certain amount of diluent, so that the diluted primer can penetrate into the base, enhance the adhesion of the coating and the base, the coating must be continuous, not interrupted, the coating amount to the surface just saturated.

3. Local leakage coating can be applied with a brush. The excess primer on the surface must be polished before the construction of the next process.

 

3. floor coating common sense of batch scraping, batch scraping material

 

In the dry (25 ℃, about 4 hours) after the primer surface using two batches of putty method, to ensure that the epoxy floor wear resistance, pressure resistance, collision, water, mineral oil, acid and alkali solution and other properties, and adjust the ground flatness.

1, with 70~140 purpose quartz sand and solvent-free epoxy batch scraping material, as the first putty, to fully stir evenly, scraping level. This road is mainly used to enhance the wear resistance and compressive properties of the ground.

2. Grind the first putty with a sand bag type dust-free rolling sander and vacuum it for cleaning.

3, with 200~700 purpose quartz sand and solvent-free epoxy batch scraping material, as the second putty, to be fully stirred evenly to enhance the wear resistance and flatness of the ground.

4. Grind the third putty with sand bag type dust-free rolling mill, and vacuum and clean it.

5. After the two putty are dry, if there are pitted surfaces and cracks, they should be repaired first, and then polished with a flat sander to smooth them and vacuum them for cleaning.

6. The number of quartz sand used shall be determined by the field engineer according to the specific conditions of the ground.

 

4. floor coating common sense of finishing epoxy floor middle layer

 

Finish the intermediate layer on the polished and cleaned putty surface (20 ℃,24 hours).

1, the finishing method can be used brush, batch scraping, high pressure airless spraying, large area construction to high pressure airless spraying is the best. (Spraying pressure is 20 ~ 25Mpa).

2, this time can make the ground more flat, more convenient to find the ground still exist defects, so that the surface layer construction leveling.

3. This time is also convenient for Party A to arrange equipment installation, etc.

 

5. floor coating common sense of finishing epoxy floor surface layer

 

1, in the middle layer of hard work (20 ℃,7 days), the epoxy solvent-free epoxy floor surface coating, coating method with batch scraping and high pressure airless spraying, but with high pressure airless spraying is appropriate.

2. Before coating, the middle layer should be polished and vacuumed with a sand bag type dust-free rolling sander.

3. If Party A has installed and debugged the equipment after the middle layer has been worked hard, resulting in new defects on the ground, it shall use batch scraping materials for leveling, polishing, vacuuming and cleaning.

4, the surface layer after spraying, such as the existence of bubbles in the application of defoaming roller, rolling back and forth on the epoxy floor, and finally let its own leveling can be.

 

6. floor coating common sense of construction matters needing attention

 

1, the construction site of the ambient temperature should be higher than 5 ℃, the relative humidity is less than 85% before construction.

2, the construction of the construction site, time, temperature, relative humidity, epoxy floor surface treatment, materials, such as the actual record, for inspection.

After the coating construction, the relevant equipment and tools should be cleaned immediately.

 

Safety technical requirements for common sense of 7. floor coating

 

1. The warning tape and warning signs shall be hung around the construction site.

2. No open fire operation and smoking are allowed within 10 meters around the construction site.

3, the use of high-pressure airless spray pump should be properly grounded.

4. Paint and thinner should be placed in a well-ventilated warehouse.

5, pay attention to personal protection when working.

6. Special personnel shall be responsible for the use of electric tools, and the power supply shall be cut off before leaving the field.

 

The use and maintenance of 8. floor coating common sense

 

1, when the paint construction is completed, do not use in the maintenance period, and must strengthen the ventilation equipment and fire prevention measures.

2, epoxy floor use, production personnel are not allowed to wear leather shoes with nails to walk on it.

3. All working instruments must be placed in a fixed special frame. It is strictly prohibited for metal parts with acute angles to collide with the ground, causing damage to the ground paint.

4, workshop installation equipment and other major objects must use lifting machinery, in contact with the ground support point should have thick rubber and other software materials pad properly, it is strictly prohibited to use iron pipes and other metals to drag equipment on the ground.

5. When high-temperature operations such as electric welding are carried out in the workshop, asbestos cloth and other refractory materials shall be applied to pave the place where electric welding sparks splash to prevent the paint from burning out.

6, once the epoxy floor is damaged, the timely use of paint repair, so as to avoid oil through the damage to penetrate into the cement, causing a large area of paint off.

7. When cleaning the ground in a large area in the workshop, do not use strong chemical solvents (toluene, banana water, etc.) to generally use detergents, soap, water, etc., and use a cleaning machine. In the absence of a cleaning machine, sawdust can be used and then cleaned.

8, winter construction, the ambient temperature is lower than 5 degrees Celsius, can be used in winter solvent-free epoxy industrial epoxy floor coatings.

9, epoxy floor surface coating formula must be strictly in accordance with the standard, the use of electronic scales according to the weight ratio, so as to ensure the quality of the floor!

 

 

 

Guangzhou Zhiye Chemical Co., Ltd. has been focusing on floor paint for 23 years. As a professional floor paint manufacturer established in the early stage of China, Zhiye has taken the lead in passing ISO management in the industry. It has always insisted on creating the greatest value for customers with continuous innovation, specializing in R & D, production, sales and application services of high-quality epoxy resin floor.

 
 

 

Address (Address):

4/F, Deputy Building, Kerui Building, 336 Qingnian Road, Huangpu District Development Zone, Guangzhou

 

Tel: 020-82057070

 

Web: www.gzzeal.com

www.gzzeal.com

020-82057070

Long press scan code can be concerned

 

 

Related News


Floor industry "high color value" products-anti-static epoxy sand self-leveling, how much do you know?

Anti-static sand self-leveling is a new type of floor coating, it has both floating sand smooth and beautiful, anti-pressure wear-resistant, light corrosion and other advantages, but also has anti-static function. It is suitable for places with high decoration, high cleanliness and antistatic requirements, such as electronics, precision instruments, chemistry, medicine, aerospace, etc., especially the production workshop and storage area of electronic instruments, integrated circuits and other components with high sensitivity to static electricity.


A brief description of the advantages and application of waterborne epoxy resin

With the introduction of environmental regulations and the awakening of environmental awareness, floor paint is a solvent-based paint with serious pollution, and VOC emissions are limited by domestic and foreign regulations. In order to meet the needs of environment-friendly and healthy life, the environmental road of the seven industries has been imperative. The "spring breeze" of the floor paint industry reform has also blown into the floor paint field, and the popularity of environmental protection products such as floor water paint has become the mainstream development direction of the industry.


Application Scenarios Overview of Waterborne Epoxy Resin

Waterborne epoxy resin refers to the epoxy resin in the form of dust, droplets, colloid dispersed in water stable dispersion system. The study of waterborne epoxy resin has been carried out abroad since the 1950 s, in which the epoxy resin is made into emulsion is a common research approach. Waterborne epoxy resins and curing agents are widely used as coatings.


Construction method for parking lot floor paint

The utility model relates to an epoxy floor, especially a parking lot floor paint construction. Epoxy floor is a kind of high strength, wear-resistant, beautiful floor, has the advantages of seamless, solid texture, good chemical resistance, anti-corrosion and dustproof, convenient maintenance, low maintenance cost and so on. Epoxy floor is widely used, parking lot floor often use epoxy floor.


Construction method and process of anti-skid parking lot floor paint

The invention relates to the technical field of construction, in particular to a construction method for anti-skid parking lot floor paint. In order to improve travel safety, some parking lots, toilets, steps, and ramps are equipped with non-slip floors to increase the friction between the soles or tires and the ground to prevent pedestrians from slipping or vehicles from slipping. However, the existing non-slip floor is expensive, and the comfort of pedestrians or vehicles is poor. Especially in rainy and foggy weather or water conditions, the anti-skid effect is poor. In addition, in the use environment of the garage, due to the weight and frequency of use of the car, cracks or peeling will appear on the surface of the floor paint, which destroys the overall beauty of the ground, and the later maintenance cost is high and there is safety.


Construction technology of parking lot floor paint

With the rapid development of real estate, more and more real estate enterprises began to attach importance to the planning and construction of underground garage, underground garage is no longer the original cement concrete. Because the construction of the underground garage is related to the image of the real estate enterprise, they all attach great importance to the beautiful and practical construction of the garage ground. For the parking lot floor paint is currently popular construction technology. The construction technology of floor paint for underground parking lot is introduced. The construction steps of the parking lot epoxy floor paint include basic treatment in the coating surface coating curing. So, epoxy floor paint primer, paint, paint how to construction? The following is the parking lot floor paint construction process in the specific steps and